Western Sydney Airport Entrance Precinct

Transport for NSW

Location
Badgerys Creek, NSW, Australia
Sectors
Transport
Western Sydney Airport Entrance Precinct

TSA Riley served as Joint Project Integrator for the Western Sydney International Airport entrance precinct, coordinating interfaces across major road, rail and utility infrastructure projects to support the airport's 2026 opening.

Western Sydney International (Nancy-Bird Walton) Airport opened to passengers on 25 October 2026, following years of construction and infrastructure development across Western Sydney. Delivering the airport required new roads, rail infrastructure, water, electricity and other utilities to connect the airport to the surrounding region and support its operation.

Many of these projects converged around the airport's main northern entrance along Elizabeth Drive. They included the M12 Motorway, airport access roads, the Elizabeth Drive upgrade and grade separation, Sydney Metro Western Sydney Airport, stormwater drainage and utility infrastructure.

Managed by separate delivery organisations, these projects had closely interconnected designs, construction activities and schedules. In June 2019, Transport for NSW engaged TSA Riley as Joint Project Integrator to manage these interfaces, coordinate activities across the precinct and support the delivery of surrounding infrastructure. The appointment was jointly funded by Transport for NSW and the Australian Government.

Our team established the Entrance Precinct Project Integration Working Group, bringing together Western Sydney Airport, Sydney Metro, Transport for NSW, Australian Government representatives and other stakeholders, including Sydney Water. The group provided a forum for coordinating activities, sharing project information and resolving interface issues across the precinct.

Through this forum and a series of technical workshops, we coordinated construction staging, analysed dependencies between project schedules and facilitated digital engineering collaboration across the different design models.

By identifying dependencies early and coordinating decisions across the different delivery organisations, TSA Riley helped the agencies address competing requirements, improve construction planning and work towards the shared objective of delivering the infrastructure needed for the airport's 2026 opening.